What Professions Are Involved In Building A Clean Room?

    The construction of the clean room is usually in the large space created by the main structure of the civil construction frame, using the decoration materials that meet the requirements, dividing and decorating according to the process requirements into a clean room that meets various requirements.

 

    The pollution control in the clean room needs to be completed by the major of purifying air-conditioning and automation. If it is a clean operating room in a hospital, medical gases such as oxygen, nitrogen, carbon dioxide, nitrous oxide, etc. need to be sent into the clean operating room. If it is a clean workshop of a pharmaceutical company, it also needs the cooperation of process pipeline and drainage profession to send the deionized water and compressed air required for pharmaceutical production into the clean room, and discharge the production wastewater into the clean room.

 

    It can be seen that the construction of a clean room must be completed by the following professions and types of work.


The required majors are as follows:

1. Civil Engineering Major

Construct the outer protective structure of the clean room.


2. Purification Air Conditioning Major

The purification air conditioning system is composed of purification air conditioning equipment, purification air pipes and valve accessories to control indoor temperature, humidity, cleanliness, wind speed, pressure difference and indoor air quality and other parameters.

 

3. Automatic control and electrical major
Responsible for the installation of clean room lighting wiring, power wiring, lamps, switch sockets and other appliances; cooperate with purifying air conditioners to realize automatic control of temperature, humidity, air supply, return air, exhaust air, indoor pressure difference and other parameters.

 

4. Process Piping Major

Various gases and liquids required by the clean room are sent into the room as required through pipeline equipment and accessories. Most of the transmission and distribution pipelines use galvanized steel pipes, stainless steel pipes and copper pipes. All the pipes installed in the clean room need to use stainless steel pipes. For deionized water pipelines, sanitary stainless steel pipes with internal and external polishing are also required.

 

5. Specialty in decoration and decoration

The "special" mentioned here means that the decoration of clean rooms is different from civil buildings. Civil architecture pays attention to the visual effects of the decorative environment and the colorful, patchy sense of hierarchy, European style, Chinese style, etc. The decoration and decoration of clean rooms have extremely strict requirements on materials: no dust, no dust accumulation, easy to clean, corrosion resistance, disinfectant scrubbing resistance, no joints or few joints (joints should be tight and flat).

The requirements for decoration and decoration are more stringent, emphasizing that the wall panels are flat, the joints are tight and smooth, and no concave and convex shapes are allowed. All the internal and external corners are made into arc corners with R>50mm; the windows should be flush with the wall , No kicking feet protruding from the wall should be set; lighting fixtures should be installed on the ceiling with a purifying lamp with a closed cover (the gap should be sealed); the ground should be made of dust-free materials as a whole, and it should be flat, smooth, non-slip and anti-static.

 

    To sum up, the construction of a clean room is a systematic project that requires close coordination between multiple professions, multiple types of work, and various professions and types of work. Any problem in the link will affect the quality of clean room construction.